| PAPER-BASED PROCEDURE | ||
|
RESPONSIBLE AGENCY Chief Inspector of Boilers Address: <Text> Phone: <Text> |
||
|
FEE Minimum Fee = Not Available Maximum Fee = Not Available |
PROCESSING TIME Minimum = Not Available Maximum = Not Available |
VALIDITY Not Available |
|
REQUIRED DOCUMENTS |
||
|
Application request on the letterhead |
||
|
PROCESS STEPS STEP 1: The trader submits the request to the Chief Inspector of Boilers for issuance of Pre-shipment Import NOC through the application on the letterhead. STEP 2: The application is then scrutinized by the Chief Inspector of Boilers. If the application documents are not complete, the trader is sent back the documents to apply again. If the application documents are complete and verified, the case is approved for the issuance of the Pre-shipment Import NOC. STEP 3: The Chief Inspector of Boilers issues the Pre-shipment Import NOC to the trader for the clearance of the Port Documents. STEP 4: The trader receives the Pre-import clearance documents.
|
||
|
PROCESS MAP
|
||
| # | عنوان | تفصیل | جاری کیا گیا | فائل |
|---|
| # | نام | تفصیل | Measure Type | ایجنسی | تبصرے | Legal Document | جواز بطرف | Measure Class |
|---|---|---|---|---|---|---|---|---|
| 1 | Pre-Shipment No Objection Certificate (NOC) for Boilers.[Import] | Importable subject to prior approval of the Chief Inspector of Boilers: Provided that used boilers will also be allowed to be imported subject to the following conditions: (i) Certification by any of the prescribed PSI companies as listed at Appendix-H for safety and remaining life of at least ten years, and (ii) Production of the certificate from Chief Inspector of boilers. | سرٹیفکیٹ کی شرائط | Chief Inspector of Boilers | The commodities that may be subject to Pre-Shipment import No Objection Certificate (NOC) for Boilers maybe Steam and vapor generating boilers (other than central heating hot water boilers capable also of producing low pressure steam) and super-heated water boilers. | Import Policy Order 2022 | 9999-09-09 | Good |