PAPER-BASED PROCEDURE

RESPONSIBLE AGENCY

Engineering Development Board (EDB)

Address:  EDB Complex Building, 5A Constitution Ave, F-5/1 F-5, Islamabad

Phone: (051) 9205595

Website: engineeringpakistan.com

FEE

 Fee= N/A

 

PROCESSING TIME

Maximum = 3 months

 

VALIDITY

1 Year

REQUIRED DOCUMENTS

  1. Technical assistance agreement with the foreign principal, if any.
  2. List of plant/machinery/equipment with complete specification, make/model, local/imported, if imported, name of the company as defined in 'Annexure-A' of the SRO.
  3. Purchase documents of plant/machinery/equipment installed as in-house facilities.
  4. Product(s) brand name to be assembled/manufactured in-house with a copy of Trademark Registration Certificate or acknowledgement receipt issued by the IPO/Trademark Registry office.
  5. List of 100% parts with %age index constituting a complete vehicle as per the attached Format-1 and comprising off:
    1. Importable components.
    2. Localized components to be procured from the vendors with their name’s contacts against each item.
    3. List of components to be manufactured in-house.
    4. Comparison of parts with parts contained under SRO 693(1)/2006.
  6. List of CKD parts to be imported under condition (iii) of the SRO for verification as per attached Format-II.
  7. List of vendors’ components to be purchased with complete description of items from the local vendors along with their complete addresses, phone, fax, email etc.
  8. Parts catalogue of vehicle duly signed and stamped.

 

PROCESS STEPS

STEP 1: After approval of quota, if during the year a new model is introduced by the Assembler and they need to avail benefit of SRO 656 (I)/2006 dated 22.06.2006 on the import of components, they may apply for addition of the of the new model in the existing approved quota along with list of components to be imported for that particular model. The list of documentary requirement is mentioned above.

STEP 2: Upon receipt of application, Assistant Manager/Deputy Manager of Engineering Development Board (EDB) evaluates application, and all attached supporting documents.

STEP 3: In case EDB Assistant Manager/Deputy Manager finds any deficiencies through the evaluation process; the officer may call additional documents/information from the Assembler and the Assembler submits the requisite documents/information.

STEP 4: After successful evaluation process, EDB designated officer verifies the documents attached with the application and submits the file to General Manager for approval to conduct physical examination, if required.

STEP 5: After approval from the General Manager, EDB designated officer along with EDB team and representatives of other relevant agencies conducts physical inspection of the manufacturing premises.

STEP 6: In case physical inspection results are satisfactory, EDB designated officer submits the report as well as proposal for addition of new model and the list of components for new model to the existing Quota List previously approved under SRO 656 (I)/2006 dated 22.06.2022 for approval by the General Manager.

STEP 7: After approval from the General Manager, EDB designated officer issues manufacturing certificate for new model and Import Quota for list of components to the Assembler and at the same time updates quota list in the WeBOC.

STEP 8: For Approval from the Chief Executive Officer, the Officer Incharge refers the Import Quota request ‘Next Level’. After approval from EDB-CEO, EDB Assistant Manager/Deputy Manager Issues Manufacturing certificate, Import Quota for list of components to the Assembler and at the same time feeds the approved quota list into the WeBOC. In case of rejection, EDB-CEO provides feedback/remarks and reverts the request to the General Manager.

PROCESS MAP

 

 

Forms
# عنوان تفصیل جاری کیا گیا فائل
Measures
# نام تفصیل Measure Type ایجنسی تبصرے Legal Document جواز بطرف Measure Class
1 Addition of New Model in Approved Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 Addition of New Model in Approved Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 with Engineering Development Board (EDB) جنرل Engineering Development Board Addition of New Model in Approved Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 with Engineering Development Board (EDB) S.R.O. 656(I)/2006 date 22-06-2006 9999-09-09 Good
کیا آپ کو یہ معلومات مفید معلوم ہوئی ہیں؟