PAPER-BASED PROCEDURE

RESPONSIBLE AGENCY

Ministry of Industries and Production/ Chief Inspector of Boilers

Address: 1st Floor, A Block Pak Secretariat, Islamabad, Pakistan

Phone:  051-9104020

Email: N/A

Website: http://www.moip.gov.pk

FEE

Minimum Fee= Not Available

Maximum Fee= Not Available

PROCESSING TIME

Minimum = Not Available

Maximum = Not Available

VALIDITY

Not Available

REQUIRED DOCUMENTS

Application on letterhead

PROCESS STEPS

STEP 1: The importer has to submit the application on Letterhead to the Chief Inspector of Boilers.

STEP 2: The officer assessed and examine the application if the officer rejected the application the importer has to resubmit the application.

STEP 3: If all the details are verified and completed, the officer releases order for port clearance

STEP 4: Importer receives the Release Order. 

PROCESS MAP

 

 

Forms
# Title Description Issued By File
Measures
# Name Description Measure Type Agency Comments Legal Document Validity To Measure Class
1 Release NOC for Imported Used Boilers [Chief Inspector of Boilers] Release NOC of imported consignment for Boilers serves as the official document for the clearance of imported consignment of boilers and related components. Certificate Requirement Chief Inspector of Boilers Application on a letterhead needs to be submitted to the Chief Inspector of Boilers for scrutiny and assessment of the case. If the application is complete, the Chief Inspector of Boiler issues the Release Order for clearance of consignment at the port. Import Policy Order 2022 9999-09-09 Good
Have you found this information useful ?
Please share your feedback below and help us improve our content.