PAPER-BASED PROCEDURE

RESPONSIBLE AGENCY

Ministry of Industries and Production/ Chief Inspector of Boilers

Address: 1st Floor, A Block Pak Secretariat, Islamabad, Pakistan

Phone:  051-9104020

Email: N/A

Website: http://www.moip.gov.pk

FEE

Minimum Fee = Not Available

Maximum Fee = Not Available

PROCESSING TIME

Minimum = Not Available

Maximum = Not Available

VALIDITY

Not Available                  

REQUIRED DOCUMENTS

Application request on the letterhead

PROCESS STEPS

STEP 1: The trader submits the request to the Chief Inspector of Boilers for issuance of Pre-shipment Import NOC through the application on the letterhead.

STEP 2: The application is then scrutinized by the Chief Inspector of Boilers.

If the application documents are not complete, the trader is sent back the documents to apply again.

If the application documents are complete and verified, the case is approved for the issuance of the Pre-shipment Import NOC. 

STEP 3: The Chief Inspector of Boilers issues the Pre-shipment Import NOC to the trader for the clearance of the Port Documents. 

STEP 4: The trader receives the Pre-import clearance documents. 

 

PROCESS MAP

 

 

Forms
# Title Description Issued By File
Measures
# Name Description Measure Type Agency Comments Legal Document Validity To Measure Class
1 Pre-Shipment No Objection Certificate (NOC) for Boilers.[Import] Importable subject to prior approval of the Chief Inspector of Boilers: Provided that used boilers will also be allowed to be imported subject to the following conditions: (i) Certification by any of the prescribed PSI companies as listed at Appendix-H for safety and remaining life of at least ten years, and (ii) Production of the certificate from Chief Inspector of boilers. Certificate Requirement Chief Inspector of Boilers The commodities that may be subject to Pre-Shipment import No Objection Certificate (NOC) for Boilers may be Steam and vapour generating boilers (other than central heating hot water boilers capable also of producing low pressure steam) and super-heated water boilers. Import Policy Order 2022 9999-09-09 Good
Have you found this information useful ?
Please share your feedback below and help us improve our content.