PAPER-BASED PROCEDURE

RESPONSIBLE AGENCY

 

 

Engineering Development Board (EDB)

Address:  EDB Complex Building, 5A Constitution Ave, F-5/1 F-5, Islamabad

Phone: (051) 9205595

Website: engineeringpakistan.com

 

 

FEE

 Fee= N/A

 

PROCESSING TIME

Maximum = 3 months

 

VALIDITY

1 Year

REQUIRED DOCUMENTS

  1. List of 100% parts with %age index constituting a complete vehicle as per the attached Format-I and comprising off:
    • Importable components
    • Localized components to be procured from the vendors with their name’s contacts against each item
    • List of components to be manufactured in-house
    • Comparison of parts with parts contained under SRO 693(1)/2006
  2. List of CKD parts to be imported under condition (iii) of the SRO for verification as per attached Format-II.

 

 

PROCESS STEPS

STEP 1: Assembler submits application for amendment in import quota along with requisite documents

STEP 2: Upon receipt of application, Desk officer from Engineering Development Board (EDB) evaluates application, and all attached supporting documents.

STEP 3: In case EDB officer – Assistant Manager/Deputy Manager finds any deficiencies through the evaluation process; the officer may call additional documents/information from the Assembler and the Assembler submits the requisite documents/information.

 

STEP 4: On completion of the evaluation process, EDB designated officer verifies the documents attached with the application.

STEP 5: In case the designated EDB officer finds the documents attached with the amendment application as satisfactory, the officer submits proposal for amendment in the approved quota to the General Manager.

STEP 6: After approval from the General Manager, the EDB designated officer notifies amendment in the Import Quota to the applicant and feeds the same into the WeBOC.

STEP 7: In case the proposal is not approved by the General Manager, it is referred to the designated officer for re-evaluation and Assembler is notified that no amendment is warranted in the already approved quota list.

 

STEP 8: For Approval from the Chief Executive Officer, the Officer Incharge refers the Import Quota request ‘Next Level’. After approval from EDB-CEO, EDB Assistant Manager/Deputy Manager Issues Import Quota for list of components to the Assembler and at the same time feeds the approved quota list into the WeBOC. In case of rejection, EDB-CEO provides feedback/remarks and reverts the request to the General Manager.

 

PROCESS MAP

 

 

Forms
# Title Description Issued By File
Measures
# Name Description Measure Type Agency Comments Legal Document Validity To Measure Class
1 Amendment in Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 Amendment in Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 with Engineering Development Board (EDB) National Standard Engineering Development Board Amendment in Import Quota of Components under SRO 656 (I)/2006 Dated 22.06.2006 with Engineering Development Board (EDB) S.R.O. 656(I)/2006 date 22-06-2006 9999-12-31 Good